When a developer completes a new housing estate and the homes are ready for occupation, the streetlights are often the last piece of infrastructure still waiting to be connected.
Unlike most electricity supplies, streetlights do not have meters. The energy they consume is calculated using industry records that identify what each asset is, where it is located and who owns it. These records are what make accurate electricity settlement and billing possible.
If the records are missing, electricity may still be flowing while the necessary industry arrangements remain outstanding. That creates billing and compliance risks.
At ESP Electricity, an Independent Distribution Network Operator serving developments across Great Britain, these records were often arriving too late. Streetlights were being energised before the supporting data existed within industry systems, which created compliance risks and generated avoidable rework.
Chantel Rocha, who works in Customer Operations at ESP, chose this as her Lean Practitioner project. She was coached through it by Master Black Belt David Hirst.
The project results
Figure 1. Unmetered supply onboarding lead time, before the project and in July 2026.
- Onboarding lead time fell from 140 days to 69 by July 2026. That is a 51% reduction against a target of 50%, measured from network award through to the point at which the meter administrator confirms the supply is registered. The improvement built steadily as the new controls came in, from 117 days in April to 92 in May, 76 in June and 69 in July.
- Two waiting periods accounted for the whole reduction. The wait for a signed connection agreement fell from 76 days to 20, and the wait for a supplier to be appointed fell from 20 days to 5.
- Process cycle efficiency doubled, from 11% to 22%. Of the original 140 days, only 15 were spent on work that added value for the customer.
- The compliance risks are now managed at the start of the process. A signed connection agreement and a confirmed supplier are both required before a supply can be registered, and a monthly audit checks every new registration.
Why the records were arriving late
Unmetered supplies include streetlights, illuminated signs, bollards, CCTV cameras and traffic signals. They are owned by developers and local authorities. ESP registers them, keeps them compliant with industry rules and makes sure a supplier is in place so that the energy can be settled and billed.
Six departments were involved in that work, from Commercial through to Regulations, with two further teams affected at either end of the process. No single department owned it from start to finish, and the effects showed up in three areas.
- Compliance. Internal and external audits had repeatedly raised the same findings, including missing connection agreements, late supplier appointments and incomplete onboarding controls. Unmetered supplies sit under industry settlement rules, and assets were being energised before that side of the process was complete.
- Revenue. A supply that is not correctly registered cannot be settled correctly, so delays at the start of the process pushed billing back at the end of it.
- Operations. When a streetlight developed a fault, the team responding to it often could not tell from the system who owned the asset, because ownership had never been recorded.
The process had grown up over time without a clear starting point, and each department was working with whatever information happened to reach it.
How the project ran
Chantel ran the project as an A3, the structure that takes a problem through to proof in eight steps. What follows is how she worked through it.
Mapping the whole process with everyone in the room
Chantel brought all eight functions together for a value stream mapping workshop. That included the faults team, who only encounter these assets once they are live. One colleague from Commercial joined on Teams so that no part of the process was missing from the discussion.
A value stream map sets out a process as it actually runs, step by step, with the waiting time between each step recorded alongside it. Mapping it as a group was important, because most of the problems sat in the handovers between departments, where no single team could see them.
The map gave everyone the same picture. The process took 140 days from start to finish. Fifteen of those days added value for the customer. The remaining 125 were spent waiting, chasing information or reworking something that had already been done. Two waiting periods, one for a signed connection agreement and one for supplier appointment, accounted for 96 of them.
Finding the root causes
The team used 5 Whys on each of the main failures, and every line of questioning led back to the same point.
Ownership of the assets was not consistently confirmed when the network was awarded, because nothing in the process required it. The working assumption had always been that it would be confirmed later on. Connection agreements had no agreed deadline and no tracking, so customers had no reason to treat them as urgent. Appointing a supplier had never been made a condition of progressing.
The constraint was not the work itself. It was that the information needed to carry out the work was not in place when the work began.
Putting the controls at the start of the process
Each of the countermeasures addresses the beginning of the process rather than the end.
- A welcome pack and automatic reminders. Customers are now told at the outset that the connection agreement must be returned within 20 working days, and what happens if it is not. Between the pack, the reminders and the deemed contract arrangement that applies once the deadline passes, the wait for a signed agreement fell from 76 days to 20.
- A control before registration. A supply cannot be registered while the signed connection agreement is still outstanding. This is a poka-yoke, a control that prevents the wrong step from being taken rather than relying on people to remember it.
- Mandatory supplier confirmation on the application form, checked before registration.
- A standard onboarding checklist that follows the process in sequence, with points at which the team cannot proceed until the required evidence is in place.
- A guidance pack for developers and connection providers, so that applications arrive complete the first time.
- Standard operating procedures and a Knowledge Hub, so that the guidance sits in one place rather than with individual team members.
One further change is still to come. A flag in the commercial quoting system will identify unmetered supply projects from the outset, rather than leaving operations to pick them up later on. It is planned for November 2026. The team deliberately left the system change until last, on the basis that a process should be standardised and brought under control first, and automated afterwards.
Keeping the improvement in place
A monthly audit now checks every new registration against the mandatory controls. Anything that falls short is tracked until it is resolved, and the results are reviewed with the Head of Customer Operations. Lead time is monitored as a KPI. Once the controls have been shown to work consistently, the audit will move to a sample.
Bringing the departments with her
At the start of the project, Chantel scored how engaged each department was. Two of the eight scored 2 out of 5. Both saw the project as additional work that had arrived from somewhere else. By the end, every department scored 5.
The value stream map is what changed that. Once people could see their own step alongside the audit finding it led to three months later, the case for change made itself.
Chantel’s advice to other practitioners is to map the whole process rather than one department’s part of it, and to bring real audit findings and examples to the discussion rather than opinions. She would do one thing differently next time. She would share the baseline data with the team before the first workshop, so that everyone arrives already understanding the scale of the problem.
David Hirst on the project
“What stood out about Chantel’s project was that she took on a problem the business had learned to work around. ESP was carrying a compliance obligation it could not consistently meet, and losing revenue to delays that had come to be accepted as normal. Rather than adding more chasing at the end of the process, she used the value stream map to show where the time was actually going, and then put the controls at the start so that the failures could not occur in the first place. Halving the lead time is the headline result. The more valuable outcome is that the process is now standardised, documented and audited, and that is what makes an improvement last.”
Congratulations Chantel
Congratulations to Chantel on completing her Lean Practitioner certification, and on delivering an improvement that reached across every part of the onboarding process at ESP Electricity.It is a good example of what the method is for. There was no additional headcount and no reorganisation. The process was mapped honestly, the root causes were traced properly, and the controls were placed where they prevent a problem rather than catch it afterwards.
Frequently asked questions
It is a live improvement project that you run in your own organisation while the training is underway, with a Master Black Belt coaching you through it. Chantel’s project is a typical example. You work on a real process with real data. The Lean Practitioner certification follows once you have completed the training and delivered an improvement project.
That depends on the process you choose. Chantel’s countermeasures went in between April and June 2026, and the improvement was measurable by July. Most projects run for a few months alongside the day job. There is no hard deadline once the training is over, although starting while the material is still fresh makes success considerably more likely.
This project is a good example of why it does. There was no production line and nothing physical to move. The waste was 125 days of waiting, chasing information and reworking something that had already been done, inside an administrative process. That is where office processes tend to hide it. Lean Practitioner is popular in service organisations for exactly this reason, because it concentrates on shortening lead times.
No. There are no entry requirements and no prior qualification is needed, so anyone can start. What matters more is bringing a real process that you want to improve. Chantel came to the training with one that had been causing problems for years, which is the strongest starting position there is.
If there is a lead time in your organisation that everyone has quietly come to accept, that is usually the right place to start. The training suits anyone looking to raise efficiency and productivity by shortening how long a process takes, whichever department they work in. Delegates bring a live process of their own and are coached through it by a Master Black Belt.
Request the prospectus for dates, formats and fees. If you are looking at this for a team rather than for yourself, talk to us about in-house training instead.